Title:Forging billet charging energy-conservation scheduling for heating furnaces efficiency
Authors: Jiang Mingming He Fei Li Dongbo Tong Yifei 
Unit: Nanjing University of Science and Technology 
KeyWords: forging heating furnace  forging billet  charging scheduling  energy-conservation scheduling  genetic algorithm 
ClassificationCode:TF089
year,vol(issue):pagenumber:2016,41(8):115-121
Abstract:

In order to achieve energy efficiency goals for forging industry, firstly, the characteristics of forging billet were analyzed, then according to specifications of forging billet heating, a forging billet charging scheduling model with an objective function, which was capacity residuals of charging, was established considering  influences of the shape and size of the forging billet on heating time. Then, based on genetic algorithm, an algorithm for objective function was constructed by genetic algorithm binary coding and elite reserved strategy. At the same time, the forging billet charging energy-saving scheduling model and its effectiveness and feasibility were verified by the relevant examples. Finally, by analyzing application examples, the amount of work time of each furnace is reduced 11 min,14 min,18 min and 15 min respectively, so the power of 1174.5 GJ is reduced for each batch of forging billet. Thus, it is proved that the energy-efficient scheduling model and solving methods meet the needs of field charging. Under the certain production conditions, the furnace utilization is effectively improved, furnace working period is shortened, and the goal of energy saving is achieved. At last, it helps to save energy in the forging process.

Funds:
国家自然科学基金资助项目(51575280)
AuthorIntro:
江明明(1989-),男,硕士研究生 何非(1982-),男,博士,讲师
Reference:


[1]Zhao Y, Liu X, Xia L, et al. Theoretical studies on the water-colded black mark of steel slab in a walking beam type reheating furnace[J]. Industrial Heating, 2005, 34(4):43-46.
[2]Si M, Thompson S, Calder K. Energy efficiency assessment by process heating assessment and survey tool (PHAST) and feasibility analysis of waste heat recovery in the reheat furnace at a steel company[J]. Renewable & Sustainable Energy Reviews, 2011, 15(6):2904-2908.
[3]Tian W, Chiu W K S. Calculation of direct exchange areas for non-uniform zones using a reduced integration scheme [J]. Journal of Heat Transfer, 2003, 125(5):839-844.
[4]Mui C, Osinski E, Meech J A, et al. A SCADA-based expert system to provide delay strategies for a steel billet reheat furnace [A]. Proceedings of the Second International Conference on IEEE [C]. Paris,1999.
[5]杨业建, 姜泽毅, 张欣欣. 钢坯热轧加热炉区生产调度模型与算法[J]. 北京科技大学学报, 2012, 34(7):841-846.Yang Y J, Jiang Z Y, Zhang X X. Model and algorithm of furnace area production scheduling in slab hot rolling [J]. Journal of University of Science and Technology Beijing, 2012, 34(7):841-846.
[6]Parali J,Malindzak D,Csonto J.Scheduling of slabs into push furnaces-two different approaches [A]. Proceedings of the 12th International Conference on Process Control and Simulation[C]. Kosice,1996.
[7]Ning S, Wang W, Liu Q. An optimal scheduling algorithm for reheating furnace in steel production [J]. Control & Decision, 2006, 21(10):1138-1142.
[8]王志刚, 刘全利, 王伟. 改进的装炉组合问题建模与优化算法[J]. 控制工程, 2011, 17(2):197-201.Wang Z G, Liu Q L, Wang W. Improved modelling and optimal algorithm for combination stacking[J]. Control Engineering of China, 2011, 17(2):197-201.
[9]朱柏青, 卢海星, 夏勇,等. 基于离散混合蛙跳算法的锻件装炉组合优化模型研究[J]. 中国农机化学报, 2013, 34(6):197-201.Zhu B Q, Lu H X, Xia Y, et al. Design and test of tractor's hydraulic steering by-wire system [J]. Journal of China Agricultural Mechanization, 2013, 34(6):197-201.
[10]孙文安, 刘发久, 孙克斌,等. 基于线性规划的炼钢装炉最小成本控制[J]. 数学的实践与认识, 2006, 36(9):158-162.Sun W A, Liu F J, Sun K B, et al. Minimum cost control of steel-making-furnacing based on linear programming[J]. Mathematics in Practice and Theory, 2006, 36(9):158-162.
[11]李颢, 任德祥. 基于遗传算法的均热炉群装炉出炉调度[J]. 控制与决策, 1999, 2(2):135-139.Li H, Ren D X. Baked charging scheduling based on genetic algorithm soaking pits [J]. Control and Decision, 1999, 2(2):135-139.
[12]史海波, 马玉林, 彭威. 冷轧企业热处理工序的优化配料装炉问题研究[J]. 计算机集成制造系统, 2004, 10(1):116-120.Shi H B, Ma Y L, Peng W. Load optimization of furnace problem for heat treatment operation of cold-rolled sheets plant [J]. Computer Integrated Manufacturing Systems, 2004, 10(1):116-120.
[13] Knoop P, Van Nerom L. Scheduling requirements for hot charge optimization in an integrated steel plant [A]. 38th IAS Annual Meeting. Conference Record of the. IEEE [C]. Utah, 2003.
[14] Baker J E.Adaptive selection methods for genetic algorithms[A].Proceedings of the 1st International Conference on Genetic Algorithms[C].Hillsdale,1987.

Service:
This site has not yet opened Download Service】【Add Favorite
Copyright Forging & Stamping Technology.All rights reserved
 Sponsored by: Beijing Research Institute of Mechanical and Electrical Technology; Society for Technology of Plasticity, CMES
Tel: +86-010-62920652 +86-010-82415085     Fax:+86-010-62920652
Address: No.18 Xueqing Road, Beijing 100083, P. R. China
 E-mail: fst@263.net    dyjsgg@163.com